Aim Print Has decided to Run their factory with the Sun!Saving them money and reducing carbon emissions daily! Terawatt installed a 80KW solar System with Generator integration which has reduced the Fuel usage on the generator. Savings on their Fuel when there is loadshedding as well as Savings on the monthly bill!A great Client and a pleasure to work with!

The system

Size80 kW
WhereKwaZulu-Natal · South Africa
Build time3 Weeks to Completion
KitJA 550w Mono Solar Panel
 Huawei 100KW Inverter
 Flush Mount on Cliplock Roofing

Our solar system was delivered with unparalleled professionalism by an exceptional design and installation team. The manner in which the Terawatt team conducted themselves and managed the project from start to finish could not be faulted.

Omar Saib · Managing Director Sancryl Chemicals
More projects

See every site we've built.

Every site we have built and commissioned, filtered by product and sector.

Browse all projects →
Talk to us

Could your site be the next one?

One bill, one site visit, one honest conversation about the numbers. We come back within one working day.

Request a site walk →
Request a site walk →
Instant AI analysis · free · POPIA-compliantUpload one bill — see your saving in plain Rands.
Upload a bill